Rural & Agrcultural Development Projects

Rural & Agricultural Development Projects

 

PROJECT NAME: MUYEXE COMMUNITY FENCING
PROJECT NATURE:

1.8M Stock Proof Fence 17 Km
1.4m Vermin Proof Fence 14 Km
1.8m Electrified Stock Proof Fence in Conjunction with a Gabion Mattress and Vermin Proof Meshing Elephant and Predator proof fencing. 14 Km Road Construction with Cattle Grids and Access Control Booms.

Client: National Department of Rural Development and Land Reform: Rural Infrastructure Development.
Province: Limpopo
District: Giyani
Township: Muyexe
Project Duration: January 2011 – March 2011
Project Monetary Value: R 12 000 000.00
   

MUYEXE COMMUNITY FENCING PROJECT: GIYANI

LIMPOPO: PROGRESS CHART: END MONTH ONE

  • MUYEXE COMMUNITY FENCING PROJECT: GIYANI LIMPOPO: PROGRESS CHART: END MONTH ONE
  • Notes
  •  Delivery of Materials is one week behind schedule due to the Road Transport Union Strike. Deployed another team as to catch up.
  • Delivery of Gabion Fence Baskets one week behind schedule due to supplier manufacturing problems.
  • Community involvement in collecting gabion stone in addition of external delivery has been finalized resulting in more benefits for them.
  • Bush Clearance completed and roads constructed to the Gabion Perimeter Fence for delivery of gabion stone.